ADOT planned on putting up barrier walls yesterday along a stretch of State Route 87 that crosses the landslide that shut the highway this past Easter weekend. The walls are intended to prevent loose soil from the slope from moving onto the highway. On Dec. 31, ADOT
reported that they saw additional movement on the landslide slope after noting movement on Dec 17, following rain in the area. [
right, ADOT contractor builds a retaining barrier at the bottom of the landslide. My photo, May 16, 2008]
ADOT says Phase Two of the SR 87 erosion control project will begin in early spring and includes the installation of a retaining wall on the west side of SR 87 and additional erosion-control measures on both sides of the highway.
No comments: